Garage Shelves

by tlp801 in Workshop > Home Improvement

43767 Views, 414 Favorites, 0 Comments

Garage Shelves

586ca34d3dd33a4de00001dd.jpeg
586c9a6f7a9cb61bfe000323.jpeg

This is an easy and affordable method I've used to build all my garage shelves. They are extremely strong and will support anything I put up there.

In this instructable I’ll walk you through a step-by-step process of how to build shelves with a little bit of engineering insight to add to your understanding of building strong structures.

Supplies, Tools, and Cost

Framing Angle.jpg
Joist Hanger.jpg
screws.jpg
strand board.jpg
Studs.jpg
level-1.jpg
square.jpg
saw.jpg
drill.jpg

Supplies & Cost

  • 2x4x8 $2.79 ea. (9 used)
  • 2x4x10 $4.30 ea. (2 used)
  • OSB 4x8 (3/8 th.) $10 ea. (2 used)
  • Screws (2.5 in.) $10
  • Framing Angles $0.50 ea. (4 used)
  • Joist Hangers $0.75 ea. (4 used)

Total: $68.71 + tax


Tools:

  • Drill
  • Level
  • Framing Square
  • Miter Saw

Time Needed:

The time to complete this project was about 2.5 hours, for the two of us, once we had all the materials needed.

Helpful Tip:

Most home improvement stores have a saw to cut down the OSB which eliminates the need for a table saw. I, almost always, have them cut it down for me.

Marking Up the Walls

587b114d1441aaa03e000505.jpeg
2015-07-17 12.19.24.jpg
586c94e9e02ad6d89a00034c.jpeg
586c94fc8852dd8aa3000342.jpeg

To make things easier I measured out lines for each and drew them on the wall using a level. This way all I needed to do was line the 2x4's up with the marks that were already made level. The only thing to really consider is the thickness of the 2x4 AND OSB that serves as the top surface of the shelf. Both of these need to be accounted for when spacing out the shelves.

Cornered In

586c95dd8ae43b8edf00032a.jpeg
586c95a29bad4bd553000308.jpeg
586c964265d221fdaa0001d4.jpeg

A square and level can be used to continue the line onto the adjacent wall.

All Lined Up

2015-07-17 12.25.55.1.jpg
586c96303dd33a4de00001cb.jpeg

As a result, you should end up with a wall full of level lines to guide the placement of each 2x4.

When securing the 2x4's up to the wall, be sure to pre-drill each hole with a bit that is slightly smaller in diameter than your screws. Doing this will help prevent the wood from splitting. I chose to place 2 screws in each stud (in the actual wall) to provide maximum support.

Note:

You can actually use 2x3's in this step to save approximately $0.80 per board.

Building Each Shelf

586c987ae02ad6d89a00035c.jpeg
586c991d9bad4b4cc70001ef.jpeg
586c99089bad4bd553000313.jpeg
586c9861ef665a26be00032d.jpeg
586c98cae02ad6d89a00035e.jpeg
586c99158ae43b20e60001d5.jpeg

Each piece of OSB was cut to 8ft x 20in

The 2x4's were cut down by about 3in to allow the top surface to overlap the boards already mounted on the walls. Therefore a 1.5in space should be made on each side of the shelf. Once aligned properly and flushed up to the edge the OSB was secured to the 2x4's using some wood screws.

Hanging Shelves

586c99329bad4b4cc70001f0.jpeg
586c993f8852ddd4e20000a2.jpeg
586c99643dd33aeaf7000331.jpeg
586c98f18080cfca95000341.jpeg
586c992b8080cfca95000342.jpeg
2015-07-17 16.07.02.jpg
2015-07-17 15.51.22.jpg

Each shelf can the be place in position on the wall and supported on the loose end with a 2x4 acting as a pillar.

Clamp the shelf to the pillar and tack a few screws along the back of the shelf to safely secure it to the wall. Repeat this process for each shelf.

The reason for only using a clamp in this stage is to allow for leveling the shelves but also giving the freedom to plumb (vertically level) the supporting pillar.

Tying It All Together

586c99e08852dd8aa300035a.jpeg
586c99abef665a25b40001d6.jpeg
586c9a1f8ae43b20e60001d9.jpeg
586c9a28e02ad6d89a000364.jpeg
2015-07-17 15.51.33.jpg
2015-07-17 15.51.29.jpg
586c9a3f7a9cb675420001ee.jpeg
2015-07-17 16.43.48.jpg

Once the pillar is plumb each shelf can be leveled across the top and screwed to the pillar. Also, I chose to give the added support of framing angles on the pillar side and joist hangers on the opposite end.

Doing this is probably overkill but it eliminates the possibility of splitting the wood (at the screws) due to excessive weight on the shelf and thereby maximizing the strength of the 2x4 beams. This is better explained in the nest step.

A Bit of Engineering Flavor

Area.JPG
formula.JPG

To further explain the reasoning in the previous step you should realize the area moment of inertia (resistance to bending) of a rectangle beam is equal to (base x height^3)/12. This means the greatest single contributor to the strength of a beam is the height of the cross-sectional area, since it's to the 3rd power. This is why an I-beam is tall and skinny. Therefore, by supporting the 2x4 beam from underneath, the strength is significantly increased.

End Supports

586c9a909bad4bd55300031b.jpeg
2015-07-18 16.51.42.jpg
2015-07-18 16.52.31.jpg

Finally, boards were cut to fit the loose end of each shelf. Doing this provides a little more stiffness across the midsection of the OSB.

Enjoy!!

586c9ac17a9cb61bfe000324.jpeg
586ca31765d221fdaa0001ea.jpeg

Now you have a very strong shelf to hold all your storage items. I've stood on these and bounced with little to no deflection in the 2x4 beams. Better yet, there are no pillars in the center obstructing the storage space.

Hopefully you were able to get something valuable out of this. If you liked it please vote for this project in the Shelving Contest.