This is the last part of Big Smelter project. I’ll finish this metal melting furnace by making refractory lining, drying, firing and finally testing. I can say that it’s my longest DIY project. It took me little more than 5 weeks to finish this work. I tested it by melting aluminum, brass and copper. The furnace passed all tests and got just minor damages.

The Refractory Mixture Formula

Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_00.15_[2017.01.19_14.51.27].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_00.36_[2017.01.19_14.52.12].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_00.55_[2017.01.19_14.52.36].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_01.25_[2017.01.19_14.53.15].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_01.57_[2017.01.19_14.54.16].jpg

The final refractory mixture formula is 50% of grog, 43% of fire clay and 7% of graphite dust. We should mix all the components and add some water. A lot of people during making refractories recommend to use less water. I don’t agree with that. In my opinion, it’s important to use a lot of water (may be the same quantity as is used for making concrete). I tried to use a small amount of water during lining the lid and it worked very bad.

Lining

Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_02.22_[2017.01.19_14.55.21].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_02.37_[2017.01.19_14.55.39].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_03.24_[2017.01.19_14.56.35].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_03.37_[2017.01.19_14.56.50].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_04.00_[2017.01.19_14.57.16].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_04.19_[2017.01.19_14.57.39].jpg

Lining the furnace with the refractory mixture.

Drying

Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_04.35_[2017.01.19_14.58.01].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_05.09_[2017.01.19_14.58.40].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_06.03_[2017.01.19_14.59.47].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_05.38_[2017.01.19_14.59.15].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_06.21_[2017.01.19_15.00.33].jpg

The next stage is drying. I’ve decided to use a bulb as a source of heat. The temperature outside was from -5 °C to +8 °C (from 23 °F to 46 °F), and rain, snow from time to time. Therefore, it wasn’t easy and quickly to dry 50 kg (110lbs) of refractory material.

Firing

Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_08.10_[2017.01.19_15.02.46].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_08.42_[2017.01.19_15.03.24].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_09.16_[2017.01.19_15.04.09].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_09.06_[2017.01.19_15.03.56].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_09.34_[2017.01.19_15.04.29].jpg
Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_10.41_[2017.01.19_15.05.40].jpg

When furnace lost most moisture it was a time to start firing. I made it very slowly. In the beginning I even didn’t blow the air inside. And after some time I could start blowing the air. During the final test the furnace was working during an hour. That’s usually enough time to melt copper.

Conclusion

Big Smelter project. Lining, Drying,Testing - Part 3 of 3.avi_snapshot_11.39_[2017.01.19_15.06.45].jpg
FHD0025.MOV_snapshot_00.09_[2017.01.19_15.08.12].jpg

I’m satisfied with the result. Now my home foundry allows me to melt and cast metals when I need it and I don’t need to fix the furnace after every melting.

If this information was interesting for you, please watch the first and the second part here: